Monday, October 8, 2007

The progress of the buildings (continued...)

This is the latest photos of the property asit was the 7th of October 2007

Briefly, they have not put the roof, but everything is ready for it except for a small part of building 1. They are working onthe wood-decoration of the building and importantly 95% of the windows and balcony doors are installed.

I'm not sure they can be finished for 15th of December, but if the works continues with the same speed as the last couple of monthes it would surely be possible to finish it before the middle of January 2008. I'm not an expert, so it might really be possible tokeep it on schedule. Drop a comment if anyone has expertise to predict a likely date of delivery!